Kingsley Village
in the heart of Cheshire

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 7 August 2020

Hi Everyone.

An early update this week as I am finishing tomorrow for a week off. I can still be contacted though if needed .

Plots 10  and 11 and the flats are now up to first lift and are currently being scaffolded ready for the next lift. The next lift on the bungalows (10,11)will take them up to wall plate height which will then see the roof trusses going on,( the trusses are being made locally at Cheshire roof trusses )

The house (5  to 9 ) are now following suit.

We have a road inspection tomorrow which will hopefully then lead to a base coat of tarmac going down.

I have issued a request to all suppliers regarding the correct way to approach site and I am going to monitor the situation very closely, Thank you to Sandie the parish clerk for coming to see me and I hope our meeting proves productive and please feel free to call again.

Finally I have a ubu road sweeper booked for this afternoon.

Thank you everybody, back on the 17th August

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 31 July 2020

Image   Image
Flats,plots 12 to 15    Bungalow, plot 10

Next week will see scaffolding arriving and plot 11 bungalow getting started .

Deliveries will be scaffolding, blocks and bricks. Also towards the end of the week a wagon of roofing tiles are due on site. 

The moment we can tarmac the roads we are looking towards our open morning . I will keep you informed 

Have a nice weekend 

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week beginning 30 July 2020

From 22nd to 24th July  the last of the block and beam flooring will be going on so we will have the crane on site for probably 2 days, and also there will be several articulated lorries carrying the beams from Cumbria.

The mortar silo is on site now, delivered last Thursday 16th July this is for the brickwork contractor who will be starting the super structure works on Monday 27th July, this is scheduled for 12 weeks but we are hoping to try and shave some time off this, that of course is also reliant on our lovely weather helping us out.

All services are on site now so there should be very little if any disturbance on Higher Heyes drive now.

The road is now ready for tarmac so once its been inspected by Cheshire West we will be laying a base coat which will be topped towards the end of the project.

We have off hired the green road sweeper now because of the formation of the road but I will be bringing in UBU sweepers as and when needed.

I really would like to  thank everyone in the village for their patience during this build, I am trying my best to keep you all happy and will try to ensure that the job runs smoothly.

Feel free to ask any questions on Facebook, email or phone, I will always try to answer them.

Many Thanks

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 

KINGSLEY PARISH COUNCIL

DAMAGED see-saw

Please DO NOT use the see-saw that is now taped off in the play area on Kingsley Playing Field.

The Council maintenance team have visited today to check it and taped it off as a warning NOT top use it. They will return tomorrow to make the area safe whilst the equipment is repaired.




Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week beginning 6 July 2020

This week the services are being brought on to site from Higher Heyes Drive by BGS. This should only take 2 to 3 days.

The bungalows (plots 3 and 4 ) now have the block and beam floor in place and we are hoping to continue with the block and beam at some stage next week.

This week I am pushing to have the road formed and hopefully soon base coated, this will stop anymore mud on the road and I will be able to off hire the road sweeper. I will however be keeping an eye on the roads and if needs be will call in UBU Sweepers.

On Friday ( 10/06/20) we will finally be getting the larger site cabins delivered and with the services being brought in then we can send the generator away.

We are only a couple of weeks away now from the superstructures being started, then you will see the houses coming out of the ground, I will give an exact date on that as soon as I can.

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 

Find us on Facebook

Latest Events

Click here for full calendar