Week beginning 6 July 2020

This week the services are being brought on to site from Higher Heyes Drive by BGS. This should only take 2 to 3 days.

The bungalows (plots 3 and 4 ) now have the block and beam floor in place and we are hoping to continue with the block and beam at some stage next week.

This week I am pushing to have the road formed and hopefully soon base coated, this will stop anymore mud on the road and I will be able to off hire the road sweeper. I will however be keeping an eye on the roads and if needs be will call in UBU Sweepers.

On Friday ( 10/06/20) we will finally be getting the larger site cabins delivered and with the services being brought in then we can send the generator away.

We are only a couple of weeks away now from the superstructures being started, then you will see the houses coming out of the ground, I will give an exact date on that as soon as I can.

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.