Works will be offline with the running of the existing roundabout mainly unaffected.

 

Week 1

Monday 15 February to Friday 19 February

 

·         Works start on site offices set-up on the grounds of the old Church by Hadfield ST (No traffic disruption)

·         Also, works start on Station Road, east of A559, on the of the existing grassed splitter island.  (There will be a single lane closure on the exit bound lane of the A559 in the vicinity of Station Road only and back to two lane traffic at the existing roundabout itself.  Lanes will be reopened in the evenings).  This will be in order to start on the car parking area to aid parking when work begins in earnest.  

·         Some trial holes to be excavated in the Station Road (no through road section) under minimal traffic management.

 

Week 2

Sunday 21 and Mon 22 February

·         Leicester Street tree clearance – Full road closure of Leicester Street between Station Road junction to the roundabout.  Access to the businesses will remain open.

Monday 22 February to Friday 26 February

·         A repeat of Week 1 with additional lane closures on the roundabout to single lane approaches in order to reduce/remove the existing splitter islands at the roundabout.

 

Many thanks.

 

Best regards

 

Vicky

 

Victoria Chowdhury  DipRSA, DipM, MCIM   
Communications and Marketing Co-ordinator – Place Operations

Cheshire West and Chester Council

( Tel: 01244 973711

Ë Mobile: 07827 823841
8 Email: vicky.chowdhury@cheshirewestandchester.gov.uk


Location: HQ (First floor RHS) / Guilden Sutton Highways Depot

Visit: cheshirewestandchester.gov.uk

My working pattern is:  In the office on Mondays (pm working at home), Tuesdays, Wednesdays and Thursdays

 

Search

Find us on Facebook

Latest Events

Click here for full calendar