Week ending 19 June 2020

Not much progress I'm afraid due to this horrendous weather.

All foundations are now in to all plots and we are aiming to have to block and beam flooring going on plots 3,4 5 and 6 on Monday 29th June.

The majority of the spoil has now been taken away so the amount of mainsway wagons should reduce now.

The weather forecast for next week is good so hopefully we will be back on track, the bricklayers have asked to work Saturday next week but obviously they wont be using any plant or machinery so will be all quiet.

Have a nice weekend everybody

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 