Week ending 4 September 2020
Photos available at https://photos.app.goo.gl/tw7pLbepjnt9xpK89
Hi All,
As promised here is an update as to where we are up to.
Superstructures are going well, the flats had their concrete hollowcore beams put on yesterday (03/09/20) so that will be the last time we need a crane on site.
Plots 11 and 10 will have the roof trusses going on next week and then the soffits and facias will go on and im looking at felt and tile somewhere around the 16th September. The rest of the plots should all start to follow suit then so there should be a continuation of trusses etc right round to plots 1 and 2 and also the flats which will be last.
I am afraid the road has not been as smooth going. Without going into too much detail the road has been held up by paperwork and red tape. The sub base has been tested to runway standards and has passed every time. Last week it had 25 tests on it and passed everyone so I am hoping there is a light at the end of the tunnel and we can finally get some tarmac down. The minute we do I will look at organising the open morning. Im hoping it will be soon because all the plots are at different stages.
My apologies for any stray wagons that have ignored the route we send them to get here, all companies are supplied with a map and directions to keep them out of the village, its not easy to police but we do try. If any do stray it would help me if you could get the companies name and let me know,that way I can deal with them direct to avoid it happening again.
Kind Regards
IAN FORBER.