Week beginning 1 June 2020

Deliveries 

Monday Wednesday and Friday (afternoon) - mortar deliveries.

We have a concrete block delivery scheduled for Monday but I am trying to postpone that for a week.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89

I estimate we are running at approx 90% capacity at the moment which for the current situation is superb.

The lads from Rigby civils are certainly pulling out all the stops and good progress is being made.

DRAINAGE – The attenuation tank went in just prior to lockdown, the Hydro brake at the site entrance is dug and concreted with the 900mm concrete surface water drain running into it from the newly formed road.

The surface water drain is to be completed week ending 29 May 2020 and from 1st June work will commence with the foul drainage to the site.

BT -  BT ducting is now in on Higher Heyes drive and while the lads where there they connected the electric ducting up to the hammer head so all that’s left to do in the drive is connection which is only very minor disturbance and I will let you know when I have a date for that.

FOUNDATIONS – We currently have plots 3 to 9 underway. Plots 3 and 4 ( Bungalows) are dug, concreted and have block work footings being built. Plots 5 and 6 are dug and concreted, Plots 7, 8, 9 are dug and were inspected on 29 May 2020.

 

 