Week beginning 8 June 2020
I plan to have the foundations in for the flats and hopefully plots 1 and 2 that will be all the foundations in then.
The foul drainage should be completed to in the new road.
On Thursday morning (11/06/2020) we are having the full site cabins delivered and the current ones removed , the new cabins are 2 @32 ft. 1@20ft and 1@10ft. They are to form the new site compound and will stay on until completion, they will not be stacked as you sometimes see on sites. Because of this, on Thursday morning we may have to park some of our cars in the road on Higher Heyes just to give the Hiab more room to work with .As soon as the cabins are down we can put the cars back on site
Deliveries next week will be just Mortar on Monday, Wednesday and Friday Pm and concrete as and when needed. Then Thursday the new site cabins. I think there will be 1 block delivery on Wednesday but I will get that confirmed.
Once the new compound is set up and the road is in I am planning on some sort of open Morning, will more than likely be on a Saturday morning where the site will be safe and I can walk round with anyone who would like to look round. Gail Farley has also suggested this and is going to help me set it up. I will keep you posted.
Have a nice weekend everybody
Kind Regards
IAN FORBER.
Site Manager
Mobile: 07764856200
Email: This email address is being protected from spambots. You need JavaScript enabled to view it.
------------------------------------
Progress Update
Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)
Good Morning all,
I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.
The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.
I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.
This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.
We have started the foul drainage now and that should be completed in the new road next week.
Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.