Kingsley Village
in the heart of Cheshire

 

Would you like to grow your own fresh fruit and vegetables and get fit at the same time?

 

 Owning your own allotment can improve both your physical and mental health. 


Dear All

Please find attached link to a temporary speed reduction notice for Meeting House Lane which commences on 18th July 2016  This is necessary for safety reasons to enable a new gas service to be installed and will be carried out by National Grid Gas Plc. The works are expected to last for 5 days

https://apps.roadworks.org/downloads/tm/5-day-notice-70014-3025777.pdf

 Should you require any further information regarding this closure, please contact on 0300 123 7036.

Regards

Technical Support Team

Winsford & Northwich Highways Office

Tel: 0300 123 7036

Email: engvr@cheshirewestandchester.gov.uk

Location: Phoenix House, Clough Road, Winsford, CW7 4BD

Visit: Cheshirewestandchester.gov.uk

 

 

Works will be offline with the running of the existing roundabout mainly unaffected.

 

Week 1

Monday 15 February to Friday 19 February

 

·         Works start on site offices set-up on the grounds of the old Church by Hadfield ST (No traffic disruption)

·         Also, works start on Station Road, east of A559, on the of the existing grassed splitter island.  (There will be a single lane closure on the exit bound lane of the A559 in the vicinity of Station Road only and back to two lane traffic at the existing roundabout itself.  Lanes will be reopened in the evenings).  This will be in order to start on the car parking area to aid parking when work begins in earnest.  

·         Some trial holes to be excavated in the Station Road (no through road section) under minimal traffic management.

 