Kingsley Village
in the heart of Cheshire

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week beginning 28 September 2020

Photos available at https://photos.app.goo.gl/tw7pLbepjnt9xpK89

Good Morning all, 

The boys from the black stuff are coming to Higher Heyes !!!!!!

I am pleased to announce we are finally getting tarmac tomorrow ( Tuesday 29 / 09/20). After weeks and weeks of testing and e mails galore we are getting the road on site base coated with tarmac.

It will take all day to complete, all wagons and plant have been instructed to approach the village the correct way so I will be keeping an eye on that one.

Obviously we wont be able to park on site on Tuesday butwill be able to from Wednesday onwards.

All plots are now under construction and are currently ranging from plots 10 and 11 which now have the roof on, down to plots 1 and 2 which are at first lift scaffold height.

The last of the roof trusses are due on site next week

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

 

  

Starting School in September 2021?
 
We are welcoming all Reception starters to visit our ‘Oasis of Hope’ 

 

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 11 September 2020

Photos available at https://photos.app.goo.gl/tw7pLbepjnt9xpK89

Morning all,

This week we have the roof trusses going on plot 10 and 11 bungalows the trusses have been made by Cheshire truss company so haven’t had too far to travel to site.

Plot 7 ( detached house) has had the floor joists and floor boards put in

Plot 8/9 is now at floor joist height and I expect them to go on towards the end of next week.

We are still waiting on a response from Cheshire west and Chester regarding tarmac to the roads, the roads passed all tests with flying colours so just a waiting game now.

Deliveries next week are

2  wagons of blocks

1 wagon of face brick

1 wagon of block paving and flags

1 wagon of timber

I will be putting a UBU sweeper on early next week and then will see about another towards the end of the week

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 11 September 2020

Photos available at https://photos.app.goo.gl/tw7pLbepjnt9xpK89

Morning all,

This week we have the roof trusses going on plot 10 and 11 bungalows the trusses have been made by Cheshire truss company so haven’t had too far to travel to site.

Plot 7 ( detached house) has had the floor joists and floor boards put in

Plot 8/9 is now at floor joist height and I expect them to go on towards the end of next week.

We are still waiting on a response from Cheshire west and Chester regarding tarmac to the roads, the roads passed all tests with flying colours so just a waiting game now.

Deliveries next week are

2  wagons of blocks

1 wagon of face brick

1 wagon of block paving and flags

1 wagon of timber

I will be putting a UBU sweeper on early next week and then will see about another towards the end of the week

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 4 September 2020

Photos available at https://photos.app.goo.gl/tw7pLbepjnt9xpK89

Hi All,

As promised here is an update as to where we are up to.

Superstructures are going well, the flats had their concrete hollowcore beams put on yesterday (03/09/20) so that will be the last time we need a crane on site.

Plots 11 and 10 will have the roof trusses going on next week and then the  soffits and facias will go on and im looking at felt and tile somewhere around the 16th September. The rest of the plots should all start to follow suit then so there should be a continuation of trusses etc right round to plots 1 and 2 and also the flats which will be last.

I am afraid the road has not been as smooth going. Without going into too much detail the road has been held up by paperwork and red tape. The sub base has been tested to runway standards and has passed every time. Last week it had 25 tests on it and passed everyone so I am hoping there is a light at the end of the tunnel and we can finally get some tarmac down. The minute we do I will look at organising the open morning. Im hoping it will be soon because all the plots are at different stages.

My apologies for any stray wagons that have ignored the route we send them to get here, all companies are supplied with a map and directions to keep them out of the village, its not easy to police but we do try. If any do stray it would help me if you could get the companies name and let me know,that way I can deal with them direct to avoid it happening again.

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

Find us on Facebook

Latest Events

Click here for full calendar