Week beginning 6 July 2020

This week the services are being brought on to site from Higher Heyes Drive by BGS. This should only take 2 to 3 days.

The bungalows (plots 3 and 4 ) now have the block and beam floor in place and we are hoping to continue with the block and beam at some stage next week.

This week I am pushing to have the road formed and hopefully soon base coated, this will stop anymore mud on the road and I will be able to off hire the road sweeper. I will however be keeping an eye on the roads and if needs be will call in UBU Sweepers.

On Friday ( 10/06/20) we will finally be getting the larger site cabins delivered and with the services being brought in then we can send the generator away.

We are only a couple of weeks away now from the superstructures being started, then you will see the houses coming out of the ground, I will give an exact date on that as soon as I can.

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 

KINGSLEY PARISH COUNCIL

Opening of the Kingsley Play & Gym Area

As per Goverment guidance the Play Area and equipment will be open from Saturday 4th July 2020

 




Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 19 June 2020

Not much progress I'm afraid due to this horrendous weather.

All foundations are now in to all plots and we are aiming to have to block and beam flooring going on plots 3,4 5 and 6 on Monday 29th June.

The majority of the spoil has now been taken away so the amount of mainsway wagons should reduce now.

The weather forecast for next week is good so hopefully we will be back on track, the bricklayers have asked to work Saturday next week but obviously they wont be using any plant or machinery so will be all quiet.

Have a nice weekend everybody

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 

Site Manager: Ian Forber | Mobile:  0776 486 5200 | Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

---------------------------

Week ending 26 June 2020

Firstly can I apologise for Friday morning, because I had to leave early on Thursday to take my daughter to the orthodontist one of the ground workers locked the gates when finishing. Unfortunately he used the wrong padlock so when I got there Friday I couldn’t get in, we had to access through the pedestrian gate and then cut the lock off to open the main gates. By this time 2 wagons where waiting to get in, It was just one of those things and hopefully wont happen again.

We have been on site today preparing for the arrival of the crane on Monday, Plots 3 / 4 / 5 and 6 are having the block and beam floor laid on Monday so we have a crane booked along with about 5 or 6 wagons with the concrete beams on.

Apart from Monday deliveries should be just a mortar delivery in the afternoons and 1 or 2 concrete deliveries through the week.

The site cabins have   been delayed until the 10th July, this is because of paperwork to United Utilities and Scottish power being held up. This will be cleared for the 6th July so we have the new cabins booked for the 10th.

Take care everyone, any questions please ask.

Kind Regards

IAN FORBER.

Site Manager

Mobile:  07764856200

Email:     This email address is being protected from spambots. You need JavaScript enabled to view it.

------------------------------------

Progress Update

Recent photographs can be viewed at https://photos.app.goo.gl/tw7pLbepjnt9xpK89 (last updated 29 May 2020)

Good Morning all,

I was going to tell you that next week the first delivery of face brick are coming but they arrived at 7.30 this morning.

The bricks we are going to use for the main build are Forterra Victorian mixture, and for the contrasting panels between some windows we are using Weinerberger smooth reds.

I am hoping to have a test panel built soon in the 2 contrasting bricks and when I do I will send a photo.

This week the surface water drainage was virtually completed, we just have the hydro brake to finish off.

We have started the foul drainage now and that should be completed in the new road next week.

Foundations – we have dug out and concreted plots 10 and 11 (bungalows ) in the top corner of the site backing on to Mansefield Road.

 

 

Natural England has just updated the Countryside Code, giving it a slight COVID-19 tweak.

Over the past few weeks there have been various instances (countrywide not necessarily in Kingsley) of people not exactly following the code as they enjoy their local footpaths and green spaces.  Please 

see the poster below ad try and follow its advice when out and about in the country side. 

The poster can also be downloaded at  https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/890511/countryside-code-poster.pdf

 

Search

Find us on Facebook

Latest Events

Click here for full calendar